+86-371-86560315

Steel platform loft installation knowledge

Apr 06, 2021

1. The unloading platform should be equipped with a load limit card.

2. The shelving point and upper tie point of the steel platform must be located on the building, and must not be installed on the scaffolding and other construction facilities, and the supporting system must not be connected to the scaffolding.

3. The concrete beams and slabs of the resting point of the steel platform should be embedded and connected with the bolts of the platform.

4. The horizontal angle between the steel wire rope and the platform should be 45 degrees to 60 degrees.

5. The tensile strength of the beams and columns at the upper part of the platform should be checked to ensure the safety of the building and the platform.

6. The platform can be lifted by a tower crane. Snap rings should be used when lifting the platform, and the hooks should not be directly hooked on the platform rings.

7. When the steel platform is installed, the wire rope should be hung firmly with special hooks. When other methods are adopted, there should be no less than 3 buckles. The sharp corners of the building should be lined with soft cushions, and the outer opening of the steel platform should be slightly higher.于内。 On the inside.

8. The left and right sides of the steel platform must be equipped with fixed railings and close-mesh safety nets.

9. The position of the steel platform should be reserved when scaffolding is erected, and the uprights of the scaffolding on both sides of the platform should be reinforced with double uprights.


Send Inquiry